EVM Glossary, A-E
Refer
to this list for definitions of essential earned value management terms submitted
by project managers from around the world. Index: A-E | F-L
| M-Q | R-Z -
A - Acceptance The formal process of accepting delivery of a product
or a deliverable. Activity The smallest self-contained unit of work used
to define the logic of a project. In general, activities share the following characteristics:
a definite duration, logic relationships to other activities in a project, use
resources such as people, materials or facilities, and have an associated cost.
Activity Definition Identifying the specific activities that must be
performed in order to produce project deliverables. Activity Duration Activity
duration specifies the length of time (hours, days, weeks, months) that it takes
to complete an activity. This information is optional in the data entry of an
activity. Work flow (predecessor relationships) can be defined before durations
are assigned. Activities with zero durations are considered milestones (milestone
value of 1 to 94) or hammocks (milestone value of 95 to 99). Activity Duration
Estimating Estimating the number of work periods that will be needed to complete
the activity. Activity File A file containing all data related to the
definition of activities on a particular project. Activity ID A unique
code identifying each activity in a project. Activity-on-Node A network
where activities are represented by a box or a node linked by dependencies. See
also Precedence Diagram Method. Activity Status The state of completion
of an activity. A planned activity has not yet started. A started activity is
in progress. A finished activity is complete. Actual Cost The cost actually
incurred. Actual Cost of Work Performed (ACWP) The sum of costs actually
incurred in accomplishing the work performed. Actual Direct Costs Those
costs specifically identified with a contract or project, based upon the contractors
cost identification and accumulation system. See also Direct Costs. Actual
Dates Actual dates are entered as the project progresses. These are the dates
that activities really started and finished as opposed to planned or projected
dates. Actual Finish Date on which an activity was completed. Actual
Start Date on which an activity was started. ACWP See Actual Cost
of Work Performed. ADM Project Non-hierarchical project that uses the
arrow-diagramming method. Advanced Material Release (AMR) A document
used by organizations to initiate the purchase of long-lead-time or time-critical
materials prior to the final release of a design. Allocation See Resource
Allocation. Alternate Resource A resource that may be substituted as
the requirement for an activity if the requested resource is not available. Approval
to Proceed Approval by the project board at initiation or prior to the beginning
of the next stage. Archive Plan A function of some computer programs
that allows versions of a plan to be archived. Arrow Diagram Method (ADM) One
of two conventions used to represent an activity in a project. Also known as Activity-on-Arrow
or i/j method. As-Late-As-Possible (ALAP) An activity for which the application
sets the early dates as late as possible without delaying the early dates of any
successor. As-Soon-As-Possible (ASAP) An activity for which the application
sets the early dates to be as soon as possible. This is the default activity type
in most project management systems. Assumptions Statements taken for
granted or truth. Authorized Unpriced Work (AUW) Any scope changed for
which authorization to proceed has been given, but for which the estimated costs
are not yet settled. Authorized Work The effort which has been defined,
plus that work for which authorization has been given, but for which defined contract
costs have not been agreed upon.
- B - Backward
Pass A procedure within time analysis to calculate the late start and late
finish dates of all activities in a project. Balanced Matrix An organizational
matrix where functions and projects have the same priority. Bar Chart A
view of project data that uses horizontal bars on a time scale to depict activity
information. Frequently called a Gantt chart. Baseline A copy of the
project schedule for a particular time (usually before the project is started)
that can be used for comparison with the current schedule. Baseline Dates Original
planned start and finished dates for an activity. Used to compare with current
planned dates to determine any delays. Also used to calculate budgeted cost of
work scheduled for earned-valued analysis. Baseline Review A customer
review conducted to determine with a limited sampling that a contractor is continuing
to use the previously accepted performance system and is properly implementing
a baseline on the contract or option under review. Baseline Schedule The
baseline schedule is a fixed project schedule. It is the standard by which project
performance is measured. The current schedule is copied into the baseline. Batch
Operations Operations performed by the computer without the need for any user
intervention. BCWP Budget Cost of Work Performed. BCWS Budget
Cost of Work Scheduled. Benefits The enhanced efficiency, economy and
effectiveness of future business operations to be delivered by a program. Benefits
Framework An outline of the expected benefits of the program, the business
operations affected and current and target performance measures. Benefits
Management Combined with program management, Benefits Management is the process
for planning, managing, delivering and measuring the program benefits. Benefits
Management Plan Specifies who is responsible for achieving the benefits set
out in the benefit profiles and how achievement of the benefits is to be measured,
managed and monitored. The Benefits Management Plan is part of the program definition. Benefits
Profiles Located in the program definition, the Benefits Profiles describe
the planned benefits to be realized by the program. The benefits profile also
states where, when and how they are to be realized. Bottom Up Cost Estimating This
is the method of making estimates for every activity in the work breakdown structure
and summarizing them to provide a total project cost estimate. Brainstorming The
unstructured generation of ideas by a group of people. Breakdown Structure A
hierarchical structure by which project elements are broken down, or decomposed.
See also Organizational Breakdown Structure (OBS) and Work Breakdown Structure
(WBS). Budget The planned cost for an activity or project. Budget
Cost The cost anticipated at the start of a project. Budget at Completion
(BAC) The sum total of the time-phased budget. Budgeted Cost of Work
Performed (BCWP) A measure used in earned value management system that allows
you to quantify the overall progress of the project in monetary terms. BCWP is
calculated by applying a performance measurement factor to the planned cost. (By
comparing BCWP with ACWP, it is possible to determine if the project is under
or over budget.) Another term for BCWP is "earned value." Budgeted
Cost of Work Scheduled (BCWS) The sum of the budgets for all planned work scheduled
to be accomplished within a given time period. This term is often used to designate
the cumulative to-date budget. Budget Element Budget elements are the
same as resources -- the people, materials, or other entities needed to do the
work of the program. For example, Engineer, Technician, Travel, and Pipe can all
be budget elements. These budget elements can be validated against a Resource
Breakdown Structure (RBS). Budget elements are typically assigned to a work package,
but can also be defined at the cost account level. Budget Estimate See
Estimate. Budgeting Time phased financial requirements. Budget
Unit The budget unit is the base unit for the calculation. For example, the
Engineer budget element might have a budget unit of hours. Since budget units
are user defined, they can be any appropriate unit of measure. For example, a
budget unit might be hours, dollars, linear feet, or tons. Burden Overhead
expenses distributed over appropriate direct labor and/or material base. Business
Assurance Ensuring that actual costs and elapsed time is in line with plan
costs and schedule times and that the business case remains available. Business
Assurance Coordinator A person in the project assurance team who is responsible
for planning, monitoring and reporting on all business assurance aspects of a
project. Business Case A document used to justify the commitment of resources
to a project.
- C - Calculate Schedule The
Critical Path Method (Calculate Schedule) is a modeling process that defines all
the project's critical activities which must be completed on time. The Calc tool
bar button on the Gantt and PERT (found in most GUI-based PM software) windows
calculates the start and finish dates of activities in the project in two passes.
The first pass calculates early start and finish dates from the earliest start
date forward. The second pass calculates the late start and finish activities
from the latest finish date backwards. The difference between the pairs of start
and finish dates for each task is the float or slack time for the task (see FLOAT).
Slack is the amount of time a task can be delayed without delaying the project
completion date. A great advantage of this method is the fine-tuning that can
be done to accelerate the project. Shorten various critical path activities, then
check the schedule to see how it is affected by the changes. By experimenting
in this manner, the optimal project schedule can be determined. Calendar
File A file containing calendar information for one or more calendars. Calendars A
project calendar lists time intervals in which activities or resources can or
cannot be scheduled. A project usually has one default calendar for the normal
work week (Monday through Friday for example), but may have other calendars as
well. Each calendar can be customized with its own holidays and extra work days.
Resources and activities can be attached to any of the calendars that are defined.
Case Structure A breakdown of the project budget. Case numbers can be
subdivided only twice to produce three levels: Case, Sub-Case, and Sub-Sub-Case. Change
Control Board (CCB) A formally constituted group of stakeholders responsible
for approving or rejecting changes to the project baselines. Change in Scope See
Scope Change. Change Requests Change requests may arise through changes
in the business or issues in the project. Change requests should be logged, assessed
and agreed on before a commitment to the project can be made. Changes may be needed
to the scope, design, methods or planned aspects of a project. Chart of
Accounts Any numbering system, usually based on corporate chart of accounts
of the primary performing organization, used to monitor project costs by category.
Child A lower-level element in a hierarchical structure. Chunk
Chart List of prioritized project work areas for a given case number and fiscal
year as part of a Dept. of Energy (DOE) Defense programs (DP) Sector Project Data
Document (PDD) Close Out The completion of work on a project. Code
File A file used in reporting that contains information associated with codes
entered on an activity record. Commitment A binding financial obligation
typically in the form of a purchase order. If commitments are entered as a budget,
a forecast using the method Retain EAC can show the open commitments. Committed
Costs Costs that will still be incurred even if the project is terminated. Communication The
transmission of information so that the recipient understands what the sender
intends. Communications Planning Determining project stakeholders
communication and information needs. Completion Date The date calculated
by which the project could finish following careful estimating. Compound
Risk A risk made up of a number of inter-related risks. Concurrent Engineering The
systematic approach to the simultaneous, integrated design of products and their
related processes, such as manufacturing, testing and supporting. Configuration The
technical description needed to build, test, accept, operate install, maintain
and support a system. Configuration Item A part a of configuration that
has a set function and is designated for configuration management. Configuration
Librarian Responsible for administering configuration management. The configuration
librarian may be on a project team or have system responsibilities rather than
project responsibilities. Configuration Management The process of defining
the configuration items in a system, controlling the release and change of those
items throughout the project, recording and reporting the status of configuration
items, and verifying the completeness of configuration items. Conflict Management The
ability to manage conflict effectively. Constraints Applicable restrictions
that will affect the scope of the project. Consumable Resource A type
of resource that remains available until consumed (for example, a material). Contingency A
Contingency is the planned allotment of time and cost for unforeseeable elements
with a project. Including contingencies will increase the confidence of the overall
project. Contingency Planning The development of a management plan that
uses alternative strategies to ensure project success if specified risk events
occur. Contract A mutually binding agreement in which the contractor
is obligated to provide services or products and the buyer is obligated to provide
payment for them. Contracts fall into three categories: fixed price, cost reimbursable
or unit price. Contract Budget Base The negotiated contract cost value
plus the estimated value of authorized but unpriced work. Contract Close-out
Settlement of a contract. Contract Target Cost (CTC) The negotiated
costs for the original definitized contract and all contractual changes that have
been definitized, but excluding the estimated cost of any authorized, unpriced
changes. The CTC equals the value of the BAC plus management or contingency reserve. Contract
Target Price (CTP) The negotiated estimated costs plus profit or fee. Contract
Work Breakdown Structure (CWBS) A customer-prepared breakout or subdivision
of a project typically down to level three which subdivides the project into all
its major hardware, software, and service elements, integrates the customer and
contractor effort, provides a framework for the planning, control, and reporting. Control
and Coordination Control is the process of developing targets and plans; measuring
actual performance and comparing it against planned performance and taking the
steps to correct the situation. Coordination is the act of ensuring that work
is being carried out in different organizations and places to fit together effectively
in time, content and cost in order to achieve the project objectives effectively. Control
Charts Control charts display the results, over time, of a process. They are
used to determine if the process is in need of adjustment. Control Control
is the process of comparing actual performance with planned performance, analyzing
the differences, and taking the appropriate corrective action. Controlling
Relationship The early dates of an activity is controlled either by a target
date on the activity or, more normally, by one of the predecessor relationships.
In the latter case, the relationship is called the controlling relationship. Coordinated
Matrix An organizational structure where the project leader reports to the
functional manager and doesnt have authority over team members from other
departments. Corrective Action Changes made to bring future project
performance into the plan. Cost Cost can be divided into internal and
external expenses. External costs can be controlled by contracts and budgets for
each phase of a project and for each deliverable or work product. Internal cost
is the cost of project resources. Cost Account A cost account is usually
defined as the intersection of the program's work breakdown structure (WBS) and
organizational breakdown structure (OBS). In effect, each cost account defines
what work is to be performed and who will perform it. Cost accounts are the focal
point for the integration of scope, cost, and schedule. Another term for Cost
Account is Control Account. Cost Account Manager (CAM) A member of a
functional organization responsible for cost account performance, and for the
management of resources to accomplish such tasks. Cost Account Plan (CAP)
The management control unit in which earned value performance measurement
takes place. Cost Benefit Analysis The analysis of the potential costs
and benefits of a project to allow comparison of the returns from alternative
forms of investment. Cost Breakdown Structure A hierarchical structure
that rolls budgeted resources into elements of costs, typically labor, materials
and other direct costs. Cost Budgeting Allocating cost estimates to individual
project components. Cost Codes Code assigned to activities that allow
costs to be consolidated according to the elements of a code structure. Cost
Control Point The point within a program at which costs are entered and controlled.
Frequently, the cost control point for a program is either the cost account or
the work package. Cost Control System Any system of keeping costs within
the bounds of budgets or standards based upon work actually performed. Cost Control
is typically a level in the budget element breakdown structure. Cost Curve
A graph plotted against a horizontal time scale and cumulative cost vertical
scale. Cost Element A unit of costs to perform a task or to acquire an
item. The cost estimated may be a single value or a range of values. Cost
Estimating The process of predicting the costs of a project. Cost Incurred Costs
identified through the use of the accrued method of accounting or costs actually
paid. Costs include direct labor, direct materials, and all allowable indirect
costs. Cost Management The effective financial control of the project
through evaluating, estimating, budgeting, monitoring, analyzing, forecasting
and reporting the cost information. Cost of Money A form of indirect
cost incurred by investing capital in facilities employed on government contracts. Cost
of Quality The cost of quality planning, control, assurance and rework. Cost
Overrun The amount by which a contractor exceeds or expects to exceed the estimated
costs, and/or the final limitations (the ceiling) of a contract. Cost Performance
Report (CPR) A monthly cost report generated by the performing contractor to
reflect cost and schedule status information for management. Cost Plus
Fixed Fee Contract (CPFF) A type of contract where the buyer reimburses the
seller for the sellers allowable costs plus a fixed fee. Cost Plus
Incentive Fee Contract (CPIFC) A type of Contract where the buyer reimburses
the seller for the seller's allowable costs and the seller earnes a profit if
defined criteria are met. Cost Reimbursement Type Contracts A category
of contracts based on payments to a contractor for allowable estimated costs,
normally requiring only a "best efforts" performance standard from the
contractor. Risk for all growth over the estimated value rests with the project
owner. Cost/Schedule Control Systems Criteria (C/SCSC) Thiry-five defined
standards which have been applied against private contractor management control
systems since 1967 in order to insure the government that cost reimbursable and
incentive type contracts are managed properly. Cost/Schedule Planning and
Control Specification (C/SPCS) The United States Air Force inititative in the
mid-1960's which later resulted in the C/SCSC. Cost Schedule Status Report
(C/SSR) The low-end cost and schedule report generally imposed on smaller value
contracts, not warranting full C/SCSC. Cost Performance Index (CPI) Ratio
of work accomplished versus work cost incurred for a specified time period. The
CPI is an efficiency rating for work accomplished for resources expended. Cost
Variance The difference between the budgeted and actual cost of work performed. Crashing The
process of reducing the time it takes to complete an activity by adding resources. Critical
Activity An activity is termed critical when it has zero or negative float.
Criticality Index Used in risk analysis, the criticality index represents
the percentage of simulation trails that resulted in the activity being placed
on the critical path. Critical Path Series of consecutive activities
that represent the longest path through the project. Critical Path Method
(CPM) A technique used to predict project duration by analyzing which sequence
of activities has the least amount of scheduling flexibility. Early dates are
figured by a forward pass using a specific start date and late dates are figured
by using a backward starting from a completion date. C/SCS See Cost/Schedule
Control Systems. C/SCSC See Cost/Schedule Control System Criteria. Customer Any
person who defines needs or wants, justifies or pays for part or the entire project,
or evaluates or uses the results. Cutoff Date The ending date in a reporting
period. CV See cost variance. -
D - Dangle An activity or network which has either no predecessors
or no successors. If neither, referred to as an isolated activity. Data
Type The characteristic indicating whether a data item represents a number,
date, character string, etc. Delaying Resource In resource scheduling,
inadequate availability of one or more resources may require that the completion
of an activity be delayed beyond the date on which it could otherwise be completed.
The delaying resource is the first resource on an activity that causes the activity
to be delayed. Delegating The process by which authority and responsibility
is distributed from Project Manager to subordinates. Deliverable A report
or product that must be completed and delivered to ensure satisfaction of contractual
requirements. Delphi Technique A process where a consensus view is reached
by consultation with experts. Often used as an estimating technique. Dependencies Dependencies
are relationships between products or tasks. For example, one product may be made
up of several other dependent products or a task may not begin until
a dependent task is complete. See also logical relationship. Dependency
Links Different types of links connecting activities in a precedence network. Design
and Development Phase The time period in which production process and facility
and production processes are developed and designed. Detailed Plans See
Detailed Resource Plan and Detailed Technical Plan. Detailed Resource Plan A
plan implemented when its necessary to plan and control a certain major
activity within a stage. The plan sets costs and resource usage that correspond
to the detailed technical plan. Detailed Technical Plan A plan used to
give a specific breakdown of major activities. It exists in all but the smallest
projects. Deterministic Network A network with no facilities to accommodate
probabilistic dependencies. Precedence networks are said to be deterministic. Direct
Costs Those costs (labor, material, and other direct costs) that can be consistently
related to work performed on a particular project. Direct costs are best contrasted
with indirect costs that cannot be identified to a specific project. Discontinuous
Activity An activity in which the interval between the start and finish dates
is allowed to exceed its duration in order to satisfy start-to-start and finish-to-finish
relationships with other activities. Discontinuous Processing This option
assigns the discontinuous attribute to all activities for a time analysis session,
except where overridden by a specific activity type. Discrete Effort Tasks
that have a specific measurable end product or end result. Discrete tasks are
ideal for earned value measurement. See Work Package. Discrete Milestone A
milestone that has a definite scheduled occurrence in time. Duration Duration
is the length of time needed to complete an activity. Duration Compression Often
resulting in an increase in cost, duration compression is the shortening of a
project schedule without reducing the project scope. -
E - EAC See Estimate At Completion. Earliest Feasible Date
The earliest date on which the activity could be scheduled to start based
on the scheduled dates of all its predecessors, but in the absence of any resource
constraints on the activity itself. This date is calculated by resource scheduling. Early
Dates Calculated in the forward pass of time analysis, early dates are the
earliest dates on which an activity can start and finish. Early Finish The
Early Finish date is defined as the earliest calculated date on which an activity
can end. It is based on the activity's Early Start which depends on the finish
of predecessor activities and the activity's duration. (See EARLY START) Most
PM software calculates early dates with a forward pass from the beginning of the
project to the end. Early Start The Early Start date is defined as the
earliest calculated date on which an activity can begin. It is dependent on when
all predecessor activities finish. Most PM software calculates early dates with
a forward pass from the beginning of the project to the end. Earned Hours The
time in standard hours credited as a result of the completion of a given task
or a group of tasks. Earned Value A cost control that allows you to quantify
the overall progress of the project in monetary terms. Earned value is calculated
by applying a performance measurement factor to the planned cost. Another term
for earned value is Budget Cost of Work Performed. Earned Value Analysis Analysis
of project progress where the actual money budgeted and spent is compared to the
value of the work achieved. Earned Value Cost Control The quantification
of the overall progress of a project in dollar terms so as to provide a realistic
yardstick against which to compare the actual cost to date. Earned Value
Management A management technique that relates resource planning to schedules
and to technical cost and schedule requirements. All work is planned, budgeted,
and scheduled in time-phased increments constituting a cost and schedule measurement
baseline. Effort The number of labor units necessary to complete the
work. Effort is usually expressed in staffhours, staffdays or staffweeks and should
not be confused with duration. Effort-Driven Activity An effort-driven
activity provides the option to determine activity duration through resource usage.
The resource requiring the greatest time to complete the specified amount of work
on the activity will determine its duration. Effort Remaining The estimate
of effort remaining to complete an activity. Elapsed Time Elapsed time
is the total number of calendar days (excluding non-work days such as weekends
or holidays) that is needed to complete an activity. It gives a "real world
view" of how long an activity is scheduled to take for completion. End
Activity An activity with no logical successors. Engineering Cost Estimate A
detailed cost estimate of the work and related burdens, usually made by industrial
engineering or price/cost estimating. Another term for Engineering Cost Estimate
is Bottom-up Cost Estimate. Enterprise-Wide Across an entire sector of
technology, business area, etc. Estimate The prediction of the quantitative
result. It is usually applied to project costs, resources and durations. Estimate
At Completion (EAC) A value expressed in either dollars and /or hours, to represent
the projected final costs of work when completed. The EAC is calculated as ETC
+ ACWP. Estimate To Complete (ETC) The value expressed in either dollars
or hours developed to represent the cost of the work required to complete a task.
Cobra calculates the ETC by subtracting the budgeted cost of work performed from
the budget at complete. The ETC is calculated as BAC - BCWP. Estimating The
act of combining the results of post project reviews, metrics, consultation and
informed assessment to arrive at time and resource requirements for an activity. ETC See
Estimate to Complete. Event A point that is the beginning or end of
an activity and identified by the I-node or J-node respectively. Exceptions
Those items that exceed the pre-defined acceptable cost and/or schedule variance.
Expected Monetary Value A measure of probabilistic value. The EMV is
calculated by multiplying each outcome value by its probability and adding all
of the results together. It can be calculated using a formula shown here. Expenditure A
charge against available funds, evidenced by a voucher, claim, or other documents.
Expenditures represent the actual payment of funds. Extended Subsequent
Applications Review (ESAR) A formal review performed in lieu of a full C/SCSC
demonstration review, when contractor conditions have changed or when programs
change External Constraint An external constraint on a project could
be any factor that affects the ability to complete the project on time, on budget,
or on scope. |