EVM Glossary, R-Z
Refer
to this list for definitions of essential project management terms submitted by
project managers from around the world. Index: A-E
| F-L | M-Q |
R-Z - R - Readiness
Assessment A meeting or series of meetings by selected members of the customer
C/SCSC review team at a contractors plant, to review contractor plans and
progress in implementing C/SCSC in preparation for a full demonstration review. Recurring
Costs Expenditures against specific tasks that would occur on a repetitive
basis. Examples are sustaining engineering, production of operational equipment,
tool maintenance, etc. Relationship A logical connection between two
activities. Relationship Float Relationship free float is the amount
by which the lag on that relationship would have to be increased in order to delay
the successor activity. Relationship total float is the amount by which it would
have to be increased in order to cause a delay in the completion of the project
as a whole (or the violation of a late target). Remaining Duration Time
needed to complete the remainder of an activity or project. Replanning Actions
performed for any remaining effort within project scope. Often the cost and/or
schedule variances are zeroed out at this time for history items. Report
Specification File A set of codified instructions, which defines the layout
of a report. Re-Profiling In resource scheduling it is possible to indicate
that the specified resource requirement profile may be modified to fit the availability,
without changing the total amount required. Request for Change A proposal
by the project manager for a change to the project as a result of a project issue
report. Request for Proposal (RFP) A bid document used to solicit proposals
from prospective sellers of products or services. Request for Quotation Equivalent
to a Request for Proposal but with more specific application areas. Requirements A
negotiated set of measurable customer wants and needs. Resource An item
required to accomplish an activity. Resources can be people, equipment, facilities,
funding or anything else needed to perform the work of a project. Resource
Analysis A term for resource leveling and resource smoothing. Resource
Assignment The work on an activity related to a specific resource. Resource
Availability The level of availability of a resource, which may vary over time. Resource
Breakdown Structure A feature of hierarchical resources that facilitates both
roll-up reporting and summary resource scheduling by enabling you to schedule
at the detailed requirements level, and roll up both requirements and availabilities
to a higher level. Resource Calendar A calendar that defines the working
and non-working patterns for specific resources. Resource Driven Task Durations Task
durations that are driven by the need for scarce resources. Resource Histogram A
view of project data in which resource requirements, usage, and availabilities
are shown against a time scale. Resource Level A specified level of
resource units required by an activity per time unit. Resource Leveling The
resource scheduling process of determining scheduled dates such that neither the
project completion date nor any target finishes are jeopardized while minimizing
the maximum extent to which any resource availability is exceeded. Resource-Limited
Resource Scheduling The production of scheduled dates in which the resource
constraints are considered as absolute and project completion is delayed as necessary
to avoid exceeding resource requirements. Resource Offset In the definition
of resource requirements, the number of work periods between the start of the
activity and when the resource is first required. Resource Optimization A
term for resource leveling and resource smoothing. Resource Period In
the definition of a resource requirement, the number of work periods for which
a resource is required. Resource Planning Evaluating what resources are
needed to complete a project and determining the quantity needed. Resource
Pool A higher level resource in a resource breakdown structure. Resource
Profile The multiple specification of a single resource requirement or availability
to indicate a variation over a period of time. Resource Requirement The
requirement for a particular resource by a particular activity. Resource
Scheduling The process of determining dates on which activities should be performed
in order to smooth the demand for resources, or to avoid exceeding stated constraints
on these resources. (See also, Resource Leveling, Time-Limited Resource Scheduling
and Resource-Limited Resource Scheduling.) Resourcing Plan Part of the
definition statement stating how the program will be resource loaded and what
supporting services, infrastructure and third party services are required. Responsibility
Assignment Matrix (RAM) The RAM correlates the work required by a Contract
Work Breakdown Structure (CWBS) element to the functional organization responsible
for accomplishing the assigned tasks. The responsibility assignment matrix is
created by intersecting the CWBS with the program Organizational Breakdown Structure
(OBS). This intersection identifies the cost account. Responsibility Chart See
Responsibility Assignment Matrix. Responsibility Matrix See Responsibility
Assignment Matrix. Responsible Organization A defined unit within the
contractors organization structure which is assigned responsibility for
accomplishing specific tasks, or cost accounts. Retainage A part of payment
withheld until the project is completed in order to ensure satisfactory performance
completion of contract terms. Reviewers Those responsible for ensuring
a product is completed and fault free at a quality review. RFC See Request
for Change. Risk The probability of an undesirable outcome. Risk
Analysis A technique designed to quantify the impact of uncertainty. Usually,
but not necessarily, associated with the Monte Carlo Simulation technique. Risk
Analysis Histogram A view in which the results of risk analysis are displayed
as vertical bars, S-curves, or tables against a date scale. Risk Avoidance Planning
activities to avoid risks that have been identified. Risk Event A discrete
occurrence that effects a project. Risk Identification Determining which
risk events will effect the project. Risk Management The art and science
of identifying and assessing the risk factors during a project and responding
to them in the best interests of the project objectives. Risk Management
Plan Part of the program definition statement that contains a record of all
the risks in the business environment, and to the program itself. Risk Matrix A
matrix with risks located in rows, and with impact and likelihood in columns. Risk
Prioritizing Ordering of risks according first to their risk value, and then
by which risks need to be considered for risk reduction, risk avoidance, and risk
transfer. Risk Quantification Evaluating the probability of risk event
effect and occurrence. Risk Ranking Allocating a classification to the
impact and likelihood of a risk. Risk Reduction Action taken to reduce
the likelihood and impact of a risk. Risk Register A file that holds
all information on identifying and managing a risk. Risk Response Control Responding
to changes in risk during a project. Risk Response Development Developing
a plan of action to enhance opportunities and decrease threats. Risks Risks
are events that if they occur can jeopardize the successful completion of the
project. Risks should be identified and assessed for probability of occurrence
and impact on the project. Risk Transfer A contractual arrangement between
two parties for delivery and acceptance of a product where the liability for the
costs of a risk is be transferred from one party to the other. Risk Value The
number obtained when numeric impact and likelihood values are multiplied. Rubber
Baselining An attempt by a contractor to take far-term budget and move it into
the current period, in an attempt to disguise cost problems. Approach will be
to move budget, but without a corresponding value of work, to mask cost difficulties.
It is an indicator of a likely cost overrun condition. -
S - Schedule A Schedule is the timetable for a project. It shows
how project tasks and milestones are planned out over a period of time. Schedule
Compression See Duration Compression. Schedule Control Controlling
schedule changes. Schedule Dates The start and finish dates calculated
by the resource scheduling program, having regard to resource constraints as well
as project logic. Schedule Development Developing a project schedule
based on activity sequences, activity durations and resource requirements. Schedule
Performance Index (SPI) Ratio of work accomplished versus work planned, for
a specified time period. The SPI is an efficiency rating for work accomplishment,
comparing work accomplished to what should have been accomplished. Schedule
Variance The difference between the budgeted cost of work performed and the
budgeted cost of work scheduled at any point in time (BCWP-BCWS). Scheduled
Finish The date calculated by the resource scheduling program as the earliest
date on which an activity can finish, having regard to resource constraints as
well as project logic. Scheduled Start The date calculated by the resource
scheduling program as the earliest date on which an activity can start, having
regard to resource constraints as well as project logic. Scheduling Scheduling
is the process of determining when project activities will take place depending
on defined durations and precedent activities. Schedule constraints specify when
an activity should start or end based on duration, predecessors, external predecessor
relationships, resource availability, or target dates. Scope The scope
is the sum of work content of a project. Scope Baseline See Baseline. Scope
Change Any change in a project scope that requires a change in the projects
cost or schedule. Scope Change Control Controlling changes to the scope. Scope
Definition Breaking down a deliverable in to smaller manageable parts to ensure
better control. Scope Verification Ensuring all identified project deliverables
have been completed satisfactorily. Scope of Work A chronological description
of the work to be accomplished or resources to be supplied. S-Curve A
display of cumulative costs, labor hours or other quantities plotted against time. Security
Plan A plan to abide by security measures related to the project. Semi-Time-Scaled
Logic Drawing A drawing in which the positioning of the activities is modified
somewhat by some date. Unlike true time-scaled drawings in which all horizontal
positions correspond to a point in time, semi-time scaled logic drawings simply
group activities whose dates fall within a specific time period. Senior
Technical A member of the project board who represents the interests of the
development and operational organizations. Senior User A member of the
project board who represent the interests of user and others affected by the project. Sequence Sequence
is the order in which activities will occur with respect to one another. This
establishes the priority and dependencies between activities. Successor and predecessor
relationships are developed in a network format. This allows those involved in
the project to visualize the work flow. SF Link See Start to Finish. Should-Cost
Estimates An estimate of the cost of a product or service used to provide an
assessment of the reasonableness of a prospective contractors proposed cost. Skill
Groups Some computer packages allow the definition of resources by their skills.
The scheduling algorithm then chooses the most appropriate resource for an activity
based on its availability and skill. Skills A feature of hierarchical
resources that allows you to assign an attribute to a resource, and to define
the resource requirement for an activity in terms of that attribute. Slippage Slippage
is the amount of slack or float time used up by the current activity due to a
delayed start. If an activity without float is delayed, the entire project will
slip. Smoothing This refers to a resource-scheduling option that modifies
the way time-limited scheduling (and resource-limited with thresholds) works.
The objective of time-limited scheduling is to minimize the maximum extent that
each resource availability needs to be exceeded, and the standard algorithm gives
itself the maximum flexibility to achieve this by making use of any excess already
incurred. The smoothing option modifies this so that it will not use the excess
for a particular activity unless necessary in order to schedule that activity
within its total float. Soft Project A project that is intended to bring
about change and doe not have a physical end product. Soft Skills Soft
skills include team building, conflict management and negotiation. Solicitation The
process of obtaining quotes, bids or proposals. Solicitation Planning Identifying
targets for quotes, bids or proposals. Source Selection Choosing from
potential contractors. Span Activity See Hammocks. Spending Plan The
total budgeted funds, based on the same subcategories as the cost plan, for a
given task area over a given fiscal year. Spending Plan Adjustments Form A
form used to change and authorize a spending plan adjustment during a fiscal year.
The form explains why the spending plan and the cost plan do not match. Splitting In
resource scheduling, it is possible to specify that an activity may be split if
this results in an earlier scheduled finish date. This means that the specified
duration may be divided into two or more pieces, while retaining the specified
profile for resource requirements relative to this split duration. SS Link See
Start to Start. Stage A subsection of a project that has its own organizational
structure, life span and manager. Stage Assessment See End Stage Assessment
and Mid-Stage Assessment. Stage File A file with the detailed management
plans and reports for the stage. Stage Manager The person responsible
for the management and successful completion of the stage. Stage Resource
Plan A plan with all of the details of the required resources for a stage. Stage
Teams A team built to complete a stage. Stage Technical Plan A plan
that states all of the technical products, activities and quality controls of
a stage. Stakeholders Stakeholders are the people who have a vested interest
in the outcome of the project. Start-to-Finish See Logical Relationship. Start
Float Start float is the amount of excess time an activity has between its
Early Start and Late Start dates. Start-To-Start Lag Start-to-start lag
is the minimum amount of time that must pass between the start of one activity
and the start of its successor(s). This may be expressed in terms of duration
or percentage. Starting Activity A starting activity has no predecessors.
It does not have to wait for any other activity to start. Many PM software packages
permit multiple start activities if needed. Statement of Work (SOW) A
description of product and service to be procured under contract; a statement
of requirements. Status Date See Time Now. Status Reports Written
reports given to both the project team and to a responsible person on a regular
basis stating the status of an activity, work package, or whole project. Status
Reports should be used to control the project and to keep management informed
of project status. Stretching In resource scheduling it is possible to
specify that an activity may be stretched if this results in an earlier scheduled
finish date. This means that the specified duration may be increased, while the
specified profile is reduced proportionally. Subcontract A contractual
document which legally defines the effort of providing services, data, or other
hardware, from one firm to another. Subnet A division of a project network
diagram representing a subproject. Subnetwork See Subnet. Subproject A
group activities represented as a single activity in a higher level of the same. Subsequent
Application Review (SAR) A review by customer personnel to determine whether
the contractor has properly applied the C/SCSC to a new contract. Successor A
successor is an activity whose start or finish depends on the start or finish
of a predecessor activity. Refer to PREDECESSOR for related information. Sunk
Costs Unavoidable costs. Super-Critical Activity An activity that
is behind schedule is considered to be super-critical. It has been delayed to
a point where its float is calculated to be a negative value. The negative float
is representative of the number of units an activity is behind schedule. System The
complete technical output of the project including technical products. System
Acceptance Letter A letter signed by the senior technical member of the project
board after ensuring the project has completed system test requirements and is
ready for user acceptance. Systems and Procedures Systems and procedures
detail the standard methods, practices and procedures of handling frequently occurring
events within the project. Systems Management Management that includes
the prime activities of systems analysis, systems design and engineering and systems
development. - T - Target Completion Date A
date which contractors strive toward for completion of the activity. Target
Date Date imposed on an activity or project by the user. There are two types
of target dates; target start dates, and target finish dates. Target Finish
-- Activity Target Finish is the user's imposed finish date for an activity.
A Target Finish date is used if there are pre-defined commitment dates. Most PM
software will not schedule a Late Finish date later than the Target Finish date.
Your favorite PM software may alert you to negative float which occurs when a
Late Finish date is later than a Target Finish date. This is caused by the duration
of predecessors which makes it impossible to meet the Target Finish date. The
negative float can be eliminated by reducing the duration of predecessors, increasing
parallelism, or extending the Target Finish date. Target Finish Date The
date planned to finish work on an activity. Target Finish -- Project A
user's Target Finish date can be imposed on a project as a whole. A Target Finish
date is used if there is a pre-defined completion date. Most PM software will
not schedule any Late Finish date later than the Target Finish date. See TARGET
FINISH ACTIVITY on how to deal with negative float. Target Schedule See
Baseline. Target Start -- Activity Target Start is an imposed starting
date on an activity. Most PM software will not schedule an Early Start date earlier
than the Target Start date. Target Start Date The date planned to start
work on an activity. Task Also called an activity. Tasks take place over
a period of time and generally consumes resources. Team A team is made
up of two or more people working interdependently toward a common goal and a shared
reward. Team Building The ability to gather the right people to join
a project team and get them working together for the benefit of a project. Team
Development Developing skills, as a group and individually, that enhance project
performance. Team Leader Person responsible for managing a stage team. Team
Members Individuals, reporting to the project manager, who are responsible
for some aspect of the projects activities. Technical Assurance The monitoring
of the technical integrity of products. Technical Assurance Coordinator A
member of the project assurance team who is responsible for reporting the technical
assurance aspects of a project. Technical Exception Unplanned situations
relating to an end product. Technical File A file that holds all of the
end products to be delivered at the end of a project. Technical Guide A
document that guides stage managers, team leaders and technical assurance coordinators
on planning the production of products. Technical Products Products produced
by a project for an end user. Three Duration Technique A method to reduce
estimating uncertainty. Time Analysis The process of calculating the
early and late dates for each activity on a project, based on the duration of
the activities and the logical relations between them. Time-Limited Resource
Scheduling The production of scheduled dates in which resource constraints
may be relaxed in order to avoid any delay in project completion. Time
Now The time at which all remaining work starts. Sometimes referred to as the
status date because all progress information entered for a project should be correct
as of this date. No work will be scheduled by the time analysis or resource scheduling
programs prior to this date. Time Recording The recording of effort done
on each activity in order to update a project plan. Time Recording Software Software
packages that build a time sheet from project planning software files and feed
actual effort back to the project plan. Time-Scaled Logic Drawing A
drawing that allows you to display the logical connection between activities in
the context of a time scale in which each horizontal position represents a point
in time. Time-Scaled Network Diagram Any project network diagram drawn
so that the positioning of the activity represents schedule. Time Sheet A
means of recording the actual effort expended against project and non-project
activities. To Complete Performance Index (TCPI) The projected performance
which must be achieved on all remaining work in order to meet some financial goal
set by management. Tolerability An accepted level of risk in order to
achieve certain benefits. Tolerance The permitted cost and timescale
limits set by the executive committee for the project or set by the project board. Top
Down Cost Estimating The total project cost subdivided for individual activities
based on historical costs and other project variables. Total Allocated Budget
(TAB) The sum of all budgets allocated to the contract. This value is the same
as the Contract Budget Base (CBB) unless an Over Target Baseline (OTB) has been
established. Total Float The maximum number of work periods by which
an activity can be delayed without delaying project completion or violating a
target finish date. Total Quality Management (TQM) A strategic, integrated
management systems for customer satisfaction that guides all employees in every
aspect of their work. Tracking Collecting actual time, cost and resource
information and putting them back into the project plan. Transition Plan Part
of the program definition statement that describes how the transition from the
current business operation to the new environment of the blueprint will be managed. Triple
Constraint Triple constraint is accomplishing performance specifications, time
schedules and monetary budgets simultaneously. Turnaround Report A report
created especially for the various responsible managers to enter their progress
status against a list of activities that are scheduled to be in progress during
a particular time window. - U - Undistributed
Budget (UB) Budget applicable to contract effort which has not yet been identified
to specific cost accounts or work packages. User Acceptance Letter A
letter prepared by the project or stage manager after ensuring that the system
complies with the user's acceptance criteria. User Assurance Coordinator The
individual who represents the users on a day-today basis and is responsible for
reporting and monitoring the user assurance components of a project. -
V - Validation A term used in C/SCSC to mean approval or compliance
with the criteria. Value A standard, principle or quality considered
worthwhile or desirable. Value Management A structured means of improving
business effectiveness that includes the use of management techniques such as
value engineering and value analysis. Variance A discrepancy between
the actual and planned performance on a project, either in terms of schedule or
cost. Variance at Completion (VAC) Variance at Complete is the algebraic
difference between Budget at Complete and Estimate at Complete. Variance
Threshold The amount of a variance which will require a formal Problem Analysis
Report, as agreed to by the contractor and the customer. Variance parameters will
differ depending on the function, level and stage of the project. Variation
Order The term used in the construction industry for an approved technical
change to the project. - W - WBS Dictionary A
document that describes each element in the WBS including a Statement of Work
(SOW), describing the work content of the WBS element, and a Basis of Estimate
(BOE), describing how the budget of the element was developed. Additional information
about each WBS element might include the responsible organization, contract number,
and so on. The WBS Dictionary will often result in the project or contract statement
of work (SOW). What-If Analysis The process of evaluating alternative
strategies. Work The total number of hours, people or effort required
to complete a task. Workaround An unplanned response to a negative event. Work
Breakdown Code A code that represents the family tree of an element
in a work breakdown structure. Work Breakdown Structure (WBS) The WBS
is a tool for defining the hierarchical breakdown and work in a project. It is
developed by identifying the highest level of work in the project. These major
categories are broken down into smaller components. The subdivision continues
until the lowest required level of detail is established. These end units of the
WBS become the activities in a project. Once implemented, the WBS facilitates
summary reporting at a variety of levels. Work Flow Work flow is the
relationship of the activities in a project from start to finish. Work flow takes
into consideration all types of activity relationships. Work Load Work
load is the amount of work units assigned to a resource over a period of time. Work
Item See activity. Work Package Detailed short-span tasks, or material
items, identified by the performing contractor for accomplishing work required
to complete a project. A work package represents a further breakdown of the work
defined by the cost account. In traditional cost/schedule systems, the criteria
for defining work packages is as follows: 1) Each work package is clearly distinguishable
from all other work packages in the program. 2) Each work package has a scheduled
start and finish date. 3) Each work package has an assigned budget that is time-phased
over the duration of the work package. 4) Each work package either has a relatively
short duration, or can be divided into a series of milestones whose status can
be objectively measured. 5) Each work package has a schedule that is integrated
with higher-level schedules. Work Products Work Products are the results
or deliverables that need to be produced in order to complete the project and
deliver the necessary changes. The work products may range from a new building
to a completed training course. Work Units Work units is the measurement
of resources. For example, people as a resource can be measured by the number
of hours they work. - Z - Zero Float Zero
float is a condition where there is no excess time between activities. An activity
with zero float is considered a critical activity. If the duration of any critical
activity is increased (the activity slips), the project finish date will slip.
|